CONSTRUCTION UPDATES

CONSTRUCTION UPDATE – ONE SYDNEY HARBOUR SITE (2023)

Works continue to progress well on the on the One Sydney Harbour construction site. The first tower, Residences One (R4A - SSD 6964), has now topped out - this means that the structure of the building reached its full height. We expect that the building will be complete later in 2023. Residences Two (R4B - SSD 6965) has also topped out and the building is expected to be complete in 2024. 

WATERMANS RESIDENCES – R5 (SSD 6966)

The third and final One Sydney Harbour tower, Watermans Residences (R5 SSD 6966), commenced construction in May 2022 and has now topped out, meaning it has reached full height. This building is located to the east of Residences One and Residences Two, by Hickson Road. The building is expected to be complete in 2024. 

HOURS OF WORK


The One Sydney Harbour standard construction hours are 7am to 7pm on Mondays to Fridays and 7am to 5pm on Saturdays. Amendment to Construction Hours for Internal works The NSW Department of Planning and Environment granted approval in May 2023 to amend the standard working hours for Residences One (Building R4A - SSD 6964) and Residences Two (Building R4B - SSD 6965) to allow internal works in these towers and the shared basement to take place during the following times:

  • Monday to Friday from 7pm until 5am (the following day)
  • Saturdays from 5pm until 5am (the following day)


The extended hours will be in place until the following dates:

  • Residences One (Building R4A) - until April 2024
  • Residences Two (Building R4B) - until September 2024
  • Shared basement - until November 2024 Permitted Works
  • All works are restricted to low noise generating activities within enclosed areas of the two towers and shared basement only.
  • Such works include (but are not limited to): floor finishes, joinery installation, mechanical and electrical installation, painting and decorating and cleaning.
  • No external construction works will be undertaken during the extended hours.
  • No high noise emitting appliances will be used during the extended hours.
  • All deliveries will take place during standard construction hours. The planning approvals can be found on the planning portal on the Department of Planning and Environment website – www.planning.nsw.gov.au


PROJECT ENQUIRIES AND COMPLAINTS

Phone: 1300 039 733 (24 hour information line)

Email: barangaroosouth@lendlease.com

Post: Locked Bag 1, Millers Point NSW 2000

A2 DOCUMENTS, STATUTORY APPROVALS, STRATEGIES

Please visit the NSW Planning Portal for all A2 Documents, Statutory Approvals and Strategies associated with R5 (SSD 6966)

SUMMARY OF ENVIRONMENTAL MONITORING

Environmental monitoring summary reports for R5 can be found here.

The Independent Environmental Audit report can be found here.

ARCHIVED REPORTS


Environmental monitoring summary reports

Independent Environmental Audit reports
 
COMPLAINTS REGISTER

The table below details complaints associated with Building R5 (SSD 6966)

Month Number of Complaints Complaint Resolution
May to November 2022 0 N/A N/A
December 2022 1 04/12/22
Noise created by chains on the jump form during shut down period.
Site team secured the chains as soon as practicable to resolve.
January 2023 2 17/01/23
Noise created by chains on the jump form.

28/01/23
Noise associated with ground works.
Site team secured the chains as soon as practicable to resolve.

Community member was provided details about the program, expected completion time and respite periods.
February 2023 1 12/02/23
Noise created by chains on the jump form.
Site team secured the chains as soon as practicable to resolve.
March 2023 0 N/A N/A
April 2023 1 29/04/23
Disturbance caused by site worker voices echoing in building.
Issue was addressed immediately with crew and subcontractors.
May 2023 0 N/A N/A
June 2023 0 N/A N/A
July 2023 0 N/A N/A
August 2023 0 N/A N/A
September 2023 0 N/A N/A
October 2023 1 20/10/23
Dust from the skip bins adjacent to Hickson Road.
Team increased mitigation measures, including using water to supress.
November 2023 1

8/11/23
Noise created from stacking of skip bins.

Team worked with subcontractor on mitigation strategies around machine use and bin placement. This continues to be monitored.
December 2023 0 N/A N/A
January 2024 0 N/A N/A
February 2024 1 15/02/24
General noise associated with skip bins.
Team worked with subcontractor on new mitigation strategies around machine use and bin placement. This continues to be monitored.